Skip to main content
My Account

Blakes, Overshot and Seven Acre House

FAQs

We're developing a major works programme for the Queensmead scheme, including Blakes House, Overshot House and Seven Acre House.

The programme will focus on addressing issues identified through surveys, inspections, repairs history, and tenant/leaseholder feedback, helping to protect and maintain the buildings for the future.

Tenants and leaseholders have reported issues including roof leaks, leaking gutters, damp and water ingress. Independent surveys and inspections have also identified work that may be needed to maintain and protect the buildings.

The proposed works are intended to address these issues and help prevent further deterioration.

The project currently covers:

  • Blakes House

  • Overshot House

  • Seven Acre House

Some elements of the project may also include garages and communal areas associated with these buildings.

The final scope of works is still being reviewed. However, the project is currently focused on external building maintenance, including areas such as roofs, gutters, brickwork, balconies, garage roofs and other repairs identified through surveys and inspections.

As part of the project review, we commissioned independent surveys and carried out further investigations to ensure the proposed works represent the best solution for the buildings.

As a result, the original proposals are being reviewed and updated to make sure the final scope reflects current building needs.

The project has undergone additional technical reviews and a reassessment of the proposed works. This has taken longer than originally anticipated, but it is important that we fully understand the condition of the buildings and develop the right long-term solution before work begins.

The programme is currently in the planning and consultation stage.

Before any major works begin, we need to finalise the scope of works, complete the necessary consultation process and appoint contractors. We will continue to provide updates as the project progresses.

The next steps include finalising the scope of works, carrying out consultation with leaseholders where required and completing the procurement process.

Once these stages have been completed, we will be able to provide more detailed information about timescales and delivery.

No. Please continue to report repairs through our usual channels.

The major works programme does not replace our responsibility to respond to day-to-day repairs, and you should continue to report any issues you are experiencing.

We do not currently expect you to move out of your home while the planned works are completed.

If any specific work requires special arrangements, affected people will be contacted directly in advance.

Major external works can create some disruption, including temporary noise, scaffolding and restricted access to certain areas while work is being carried out.

We will work with contractors to minimise disruption wherever possible and will provide you with advance notice of significant activities.

Some works may require temporary restrictions to access in certain areas for safety reasons.

Where this is necessary, we'll inform you in advance and alternative arrangements will be considered where possible.

Leaseholders will be consulted through the appropriate statutory consultation process for major works.

We will provide information about the proposed works, explain the next steps and offer opportunities for leaseholders to ask questions throughout the process.

The scope of works is currently being reviewed and no final decisions have been made on all elements of the project.

Any proposals that form part of the final scope will be communicated as part of the consultation and engagement process. Earlier consultations included discussion about cladding and alternative approaches to external repairs.

We'll continue to share updates throughout the project.

If you have a question about the Queensmead major works programme, please contact Chris Lambert: